Work Instruction – Releasing Cash Retention
Version 1.0 31/10/2017
Document Author |
Document Owner |
Rika Mason |
Rika Mason |
Purpose:
This document will explain how to Release Retention in Viewpoint
Document Flowchart: JB Progress Billing
JB Release Retention
JB Progress Billing
Pre-requisites
- Viewpoint Login ID & Viewpoint (Remote) is mandatory for using Viewpoint outside head office
Process:
- Log into Viewpoint
- Open JB Progress Billing (Main Menu) or Create a Progress Claim from your work centre
- Create claim, Enter Certification Month, Enter + or N in the record field to create a new claim, Enter Contract Number, Update Invoice Description, Add notes and amend completed works period ending date
- Go to Main Menu and search for ‘JB Release Retention’, drag and drop into My Tasks so it’s easily accessible – open it, it should have automatically come up with your contract/job number
- Complete JB Release Retention form – example below
- Select OK
- Select Close
- Open JB Progress Billing again with your claim you created. Press the retainage button at the bottom of the screen on the info tab to check Retainage Totals are correct
- Check the retention amount to be released is correct and close form
- Select ‘Update Claim Totals’ and check that the amount is correct, if everything is correct you can Print/Submit Claim – Remember to export and ‘Attach to Form’ so it shows in your thumbnail viewer
- Once a payment certificate is received from the superintendent go back into the claim that was created and certify. Drag and drop a copy of the payment certificate into the thumbnail viewer. Save and close this form